1 - Urban Planning and City Development Plan
1 Preparation of Master Plan using GIS (State Level) Mar 2019 1. Contract awarded/Certificate of in-house master plan formulation.

2. Base map prepared

3. Draft master plan is prepared.

4. GIS based master plan is notified.
Executing Agency CTCP, UP (Chief Town & Country Planner, U.P.)
2- Urban Planning
1 Develop one park per AMRUT city every year (Year 2015-16, 2016-17, 2017-18) Mar 2019 Development/Construction and value addition in a park with children's facilities. Shyam nagar C block park Zone 2 Ward no. 74 has been developed in 2018-19. Work Order and photographs have been attached.

ANNEX 2

3 - Double Entry Accounting
1 1.Implementation of Accrual based Double Entry Accounting System.

2. Publication of Audited Balance Sheet/of Annual Financial Statement on website (Year 2015-16, 2016-17, 2017-18)
Mar 2019 1). 2012-13 - Completed
2). 2013-14 - Completed
3). 2014-15 - Completed
4). 2015-16 - Completed
5).2016-17 – Completed
6).2017-18 – Completed

http://kmc.up.nic.in/knnbudget.htm
Snapshot of audited statement of last two years as published on website.

ANNEX 3.1.1

http://kmc.up.nic.in/knnbudget.htm
2 Financial Statement of current F.Y. 2018-19 on website Mar 2019 1Financial Statement of current F.Y.2018-19 on uploaded on the website.

http://kmc.up.nic.in/knnbudget.htm
ANNEX 3.2

http://kmc.up.nic.in/knnbudget.htm
                    Ø DOWNLOAD AMRUT REFORM IN PDF FORMAT